One Cent Makes Sense

On November 4, 2008, the voters of Berkeley County passed a one percent sales and use tax for "financing the costs of highways, roads, bridges, and other transportation-related project facilities, and drainage facilities related thereto." This tax will last for seven years and all the revenue generated will be used to construct roadway improvements including the projects listed in the approved referendum. Collection began the following May and the first revenue was received in October of 2009. As of July 2014, a total of $95,000,607.81 has been collected. At this rate, $133 million will be collected over seven years.

This site is dedicated to keeping Berkeley County citizens informed on the progress of projects being constructed with your transportation sales tax. Please select a project below to review the status.

Titlesort descending Project Status Status Report Pictures
Ambassador Avenue In the process of addressing sight distance issue... Ambassador Avenue-- 3rd Quarter 2017.pdf
Arthur Gillins Lane Construction of this project is complete.
Avery Drive Construction of this project is complete.
Benjamin Drive Design is underway and a Spring 2018 construction... Benjamin Drive-- 3rd Quarter 2017.pdf
Beulah Tabernacle Road Working through permitting issues with US Army... Beulah Tabernacle Road --3rd Quarter 2017.pdf
Black Tom Road (US 176 to Black Tom Extension) SCDOT is managing the project for Berkeley County... Black Tom Road (US 176 to Black Tom Extension) -- 3rd Quarter2017.pdf
Blanding Road Construction of this project is complete.
Calestown Road Construction of this project is complete.
Clements Ferry Road Widening Phase 1 Construction underway consisting primarily of... Clements Ferry Phase 1 --3rd Quarter 2017.pdf
Clements Ferry Road Widening Phase 2 (From Jack Primus Road to SC 41) Preliminary geometric design is underway. A... Clements Ferry Phase 2 --3rd Quarter 2017.pdf
Coaxum Road Final design is complete and final construction... Coaxum Road -- 3rd Quarter 2017.pdf
Crawford Road Construction of this project is complete.
Daniel Island Drive at Seven Farms Drive Preliminary plans are complete and have been... Daniel Island Drive at Seven Farms Road -- 3rd Quarter 2017.pdf
Dennis Drive Design is progressing and coordination with CSX... Dennis Drive -- 3rd Quarter 2017.pdf
Dr. Evans Road (Hard Pinch Road to end) SCDOT is managing the project for Berkeley County... Dr.Evans Road (Hardpitch Road to end) -- 3rd Quarter 2017.pdf
England Road Final design is being reviewed and an... England Rd-- 3rd Quarter 2017.pdf
Farm Hill Circle Construction of this project is complete.
Fauling Road Final design is complete and final construction... Fauling Road -- 3rd Quarter 2017.pdf
Fennick Drive Construction of this project is complete.
Firehouse Road Construction of this project is complete.
Foster Creek Road at Tanner Ford Boulevard The project is currently in the pre-construction/... Foster Creek Road at Tanner Ford Boulevard -- 3rd Quarter2017.pdf
George Wigfall Road Construction of this project is complete.
Green Bay Road Construction of this project is complete.
Henry Brown Boulevard Widening Phase 1 The project is currently under construction.... Henry Brown Boulevard Widening Phase 1 -- 3rd Quarter 2017.pdf
Henry Brown Boulevard Widening Phase 2 (Liberty Hall Road to Old Mt. Holly Road/ US 52) The project is currently in the pre-construction/... Henry Brown Boulevard Widening Phase 2 (Liberty Hall Road to OldMt. Holly Road US 52) -- 3rd Quarter 2017.pdf
Hoodtown Road (US 17 Alt. to Schurlknight Road) SCDOT is managing the project for Berkeley County... Hoodtown Road (US 17 Alt. to Schurlknight Road) -- 3rd Quarter2017.pdf
Jacob Piland Road Final design is complete and final construction... Jacob Piland Road -- 3rd Quarter 2017.pdf
Jedburg Road/ I-26 Interchange ( Right of way acquisition only) Right of way is complete. This interchange... Jedburg Road I26 Interchange ( Right of way acquisition only) --3rd Quarter 2017.pdf
Mitchum Town Road Construction of this project is complete.
Moultrie Lane Construction of this project is complete.
Mourning Dove Drive Construction of this project is complete.
Mudville Road (US 176 to Ranger Drive) SCDOT is managing the project for Berkeley County... Mudville Road (US 176 to Ranger Drive) -- 3rd Quarter 2017.pdf
Murray Drive at Hanahan Road Construction of this project is complete.
Murray Drive at Yeamans Hall Road Plans are complete. No new right of way required... Murray Drive at Yeamans Hall Road -- 3rd Quarter 2017.pdf
N. Highway 17 at Highway 41 Construction of this project is complete.
Nexton Parkway at Cane Bay The project is currently in the right of way... Nexton at Cane Bay -- 3rd Quarter 2017.pdf
Nexton Parkway/I-26 Interchange and I-26 Widening The project is currently under construction.... Nexton Parkway I26 Interchange -- 3rd Quarter 2017.pdf
Old Highway 52 (0.2 miles east of US 52 to US 52 in Strawberry) SCDOT is managing the project for Berkeley County... Old Highway 52 (0.2 miles east of US 52 to US 52 in Strawberry) --3rd Quarter 2017.pdf
Railroad Avenue Extension The project is currently in the pre-construction/... Railroad Avenue Extension Project -- 3rd Quarter 2017.pdf
Royle Road at Sangaree Parkway Conceptual designs have been completed for a... Royle Road at Sangaree Parkway -- 3rd Quarter 2017.pdf
SC 402 (Turnaround Court to Alligator Road) SCDOT is managing the project for Berkeley County... SC 402 (Turnaround Court to Alligator Road) -- 3rd Quarter2017.pdf
SC 45 (Edgewater Road to US 52 in St. Stephen) SCDOT is managing the project for Berkeley County... SC 45 (Edgewater Road to US 52) -- 3rd Quarter 2017.pdf
SC 6 (Pinopolis Road to CSX RR) SCDOT is managing the project for Berkeley County... SC 6 (Pinopolis Road to CSX RR) -- 3rd Quarter 2017.pdf
Spring Pond Road Construction of this project is complete.
Starks Croker Drive Final design is complete and final construction... Starks Croker Drive -- 3rd Quarter 2017.pdf
Stevensridge Lane Construction of this project is complete.
Timberline Way Final design is complete and final construction... Timberline Way-- 3rd Quarter 2017.pdf
Tobacco Road Construction of this project is complete.
US 176 Widening – Phase 1 (US 17A to Jedburg Road/Cooper Store Road) Project design is underway. Surveys, utility... US 176 Widening Phase 1 -- 3rd Quarter 2017.pdf
US 176 Widening – Phase 2 (Jedburg Road/Cooper Store Road to Center Line Road) Project design is underway. Surveys, utility... US 176 Widening Phase 2 -- 3rd Quarter 2017.pdf
US 52/ US 176 Interchange – Goose Creek The project is currently in the conceptual design... US 52 US 176 Interchange Goose Creek -- 3rd Quarter 2017.pdf
Wilder Road Construction for this project is complete.
Zion Road Construction of this project is complete.